Timeline 2023
Phase 1 will commence in November 2023 taking approx. 20 weeks. The physical works included in Phase 1 are:
- At Sean Healy Park – construction of new footpaths, hard paved areas and widening of the Suir Blueway including associated landscaping and services/utilities to serve the proposed and future uses.
- The Suir Blueway will be extended to connect to North Quay to provide cycleway and pedestrian linkages from Sean Healy Park to Ormond Castle.
- Upgrade of the Castle Street approach to Ormond Castle Park.
- Undertaking of ecological and amenity improvements within Castle Park grounds including new lighting along Strand Walk and repointing of Castle Park walls.